Target Information

Goal: National roads and bridges
Objective: Bridges

Target: G100601 - Rehabilitation of bridges


Deadline: 31-12-2013

Target: 100.00 Percentage

Actual: 80.00 Percentage



Rehabilitation of bridges

Public to private sector: Public to private sector

Fund: Infrastructure Fund

Institution: Ministry Infrastructure , Sec Est Transport ComunicaƧƵes

Location: National Region , National Region , National Region

Sector: Infrastructure Development , Roads and Bridges

Age: All ages

Gender: Males and Females

The Ministry of Infrastructures intends to allocate budget for this project with the goal to make the rehabilitation of bridges throughout the territory that are spoiled, so users can have permanent access to the road network for their day-to-day activities.
This project has been budgeted in 2011 but is still in the process of preparing the technical design for the bridges that are damaged.
This project should be implemented in order to rehabilitate bridges that are spoiled to ensure continued access to the country's road network.
During the build process, the project will result in direct and indirect benefits to the local population and creation of jobs. When completed it will bring positive results for the development of the economy.
Will contribute in social life and in economic development when its physical implementation is completed.
After implementation it will contribute to poverty reduction because it would create employment opportunities.


There are five bridges belonging to this task:

  • Bemos Bridge
  • Mola Bridge
  • Ulmera Bridge
  • Alpelu Bridge
  • Manciga Bridge
Four of them have been completed in full:
  • Bemos Bridge
  • Mola Bridge
  • Ulmera Bridge
  • Alpelu Bridge


Physical vs Financial Progress

Physical Progress
Base Line 0 0%
Actual 80 80%
Target 100 100%

Financial Progress