Target: G030101 - Taibesi Market (Manleuana)
Status: FINISHED
Deadline: 31-12-2012
Target: 100.00 Percentage
Actual: 100.00 Percentage
Taibesi Market (Manleuana)
Fund: Infrastructure Fund
Institution: Min Turismo,Comercio,Industri , Industry and Comerce
Location: Dili , Dom Aleixo , Bairro Pite
Sector: Economic Development , Rural Development
Age: All ages
Gender: Males and Females
This project was originally programmed for re-constructing of Taibessi market. However, this project cannot be executed due to technical constraints related to removal of the existing occupants from the targeted project site, and the project has been on hold for more than six months. With this development and on the recommendation of MTCI, CAFI approved MTCI request to re-allocate the fund to finance construction of Manleuna Market Phase III.
| Percentage | ||
|---|---|---|
| Base Line | 0 | 0% |
| Actual | 100 | 100% |
| Target | 100 | 100% |